The Jan. 15, 2014 Pope/Chaucer Project Public Meeting video is online at YouTube

The video provides a comprehensive overview of the San Francisquito Creek Plan and how the Pope/Chaucer Street Bridge Replacement Project fits into that plan.

00:00 to 18:20    Introduction and Flood Protection Program
            11:23 to 13:30    Highway 101 is 8-year [at high tide], Pope/Chaucer a 15-year
            12:51 to 13:30    Newell, University and Middlefield are all about 35-year bridges

18:20 to 36:58    Pope/Chaucer Bridge Replacement Presentation

36:58 to 1:34:45 Questions and answers