SCVWD Proposed Floodwall Alternatives
| Red lines indicate a total of almost 2 miles of floodwalls (about 1/2 mile on each side of the creek at each bridge) |
SCVWD Alternative 1 – Raised Bridge & Future Floodwalls
Interim design proposal (current project)
· Construct new bridge with an approximately four feet higher road profile.
· Requires raising roadway elevations at bridge and approaches.
(Chaucer St, Palo Alto Ave, Woodland Ave).
(Chaucer St, Palo Alto Ave, Woodland Ave).
· Construct retaining walls at the four corner properties.
Impacts
· We lose the Oaks, the other trees, and the mini-park on the current bridge.
· We lose the street trees on the four corner properties.
· The creek bank is armored with rock for up to 200’ upstream & downstream.
· We lose the trees on the creek banks up to 200’ upstream & downstream.
100-year design proposal (potential future project)
· Requires three-foot-tall bridge railings.
· May require six-foot-tall, tapering to three-foot-tall floodwalls, which could extend up to 600’ upstream of the bridge.
Impact
· Added to the interim design losses, we lose the Oaks on the creek banks for up to an additional 400’ upstream and downstream, a total of 1200’ ≈ 1/4 mile.
SCVWD Alternative 2 – “Slightly Higher” Bridge & Future Floodwalls
(Now "one to two feet higher" than existing road per SCVWD)
(Now "one to two feet higher" than existing road per SCVWD)
Interim design proposal (current project)
· Construct new bridge with a slightly higher profile than the existing road.
· Requires minimal changes to roadway elevations at bridge and approaches.
Impacts
· We don’t lose the street trees on the four corner properties.
· We lose the Oaks, the other trees, and the mini-park on the current bridge.
· The creek bank is armored with rock for up to 200’ upstream & downstream.
· We lose the trees on the creek banks up to 200’ upstream & downstream.
100-year design (potential future project)
· Requires approximately seven-foot-tall bridge headwall.
· May require seven-foot-tall tapering to three-foot-tall floodwalls, which may extend up to 1,800’ upstream of the bridge.
Impact
· In addition to the interim design losses, we lose the Oaks on the creek banks for up to an additional 1600’ upstream and 400’ downstream, a total of 2400’ ≈ 1/2 mile.